ADF/SERIALS
Australian & New Zealand Military Aircraft Serials & History

RAAF A73 Avro/GAF Lincoln Mk.30 & Mk.31

Powered by FreeFind

Site search
Web search
Hosted by:

Integrity Technical Solutions

 

Lincoln A73-73

 
     
 

Main Lincoln Page

 

Lincoln Image Gallery

 
     
 

Government Aircraft Factory (GAF) monthly Lincoln production reports (from August 1951to October 1953)

 
     
 

This is the data from the monthly production reports, which consist of a written report and a table setting out expected, actual and cumulative production.  The reports to April 1953 are signed by V. F. Letcher, Director of Aircraft Production.  From May 1953 signed by S. C. Wheetman for Assistant Secretary (Aircraft Production)

August 1951

 One Lincoln aircraft to a total of 62 was competed by the GAF during August.  Delivery, however, was not to be made to the RAAF since this and the 11 aircraft remaining to complete the project plus eight aircraft to be returned by the RAAF are to be converted for GR purposes.  Table says 0 produced this month, cumulative production total 61.

September 1951

No Lincoln aircraft were delivered to the RAAF by the GAF during September, total deliveries being 61 at the end of the month. Since the 12 aircraft remaining to complete the project are to be converted for GR purposes before delivery together with eight aircraft to be returned by the RAAF for that purpose, it is not anticipated that further Lincoln aircraft will be delivered before March 1952. Table says 0 produced this month, cumulative production total 61.

October 1951

As was explained in the preceding report, it is not anticipated that further deliveries of Lincoln aircraft will be made by the GAF until March 1952 since aircraft beyond No. 61, which was delivered during September 1951, to the total of 73 are to be converted for GR purposes before delivery to the RAAF together with eight more Lincoln aircraft to be returned by the RAAF from service. Table says 0 produced this month, no cumulative production total given.

November 1951

No deliveries of Lincoln aircraft were made by the GAF during November.  Further deliveries beyond aircraft No. 61 will not, it is anticipated, be made until March 1952 approximately since subsequent aircraft, up to the project total of 73, together with eight aircraft to be returned from RAAF service, are to be converted for GR purposes before delivery. Table says 0 produced this month, cumulative production total 61.

December 1951

No further Lincoln bomber aircraft beyond the 61st which was delivered to the RAAF in July 1951, will be delivered by the GAF until March, 1952, since the 12 remaining to complete the project, together with eight to be returned from service by the RAAF are to be extensively modified for GR purposes. Manufacture of the extra fuselage units and details required for the modifications progressed during December. Table says 0 produced this month, cumulative production total 61

January 1952

Manufacture of the extra fuselage units and details required for the conversion for GR purposes of Lincoln bomber aircraft beyond aircraft No. 61 proceeded at the GAF during January. Delivery of the converted aircraft will be delayed beyond the scheduled date because certain essential airframe equipment cannot be obtained in time from the United Kingdom. Table says 0 produced this month, cumulative production total 61.

February 1952

During February arrangements proceeded at the GAF for the conversion for GR purposes of the twelve Lincoln aircraft remaining to complete this project and of eight more aircraft to be returned by the RAAF. Certain shortages of parts from overseas will probably make it necessary to complete the prototype up to the stage of flight trials and to incorporate the remaining items as the parts become available. Table says 0 produced this month, cumulative production total 61.

March 1952

Work was continued at the GAF during March in connection with the conversion for GR purposes of the 12 Lincoln aircraft remaining to complete this project and of eight more aircraft to be returned from service by the RAAF. Shortages of parts from overseas had an adverse effect on progress and it will be necessary to flight test the prototype aircraft in an incomplete condition because of this. Within the limits of the shortages, work was done on the 12 new aircraft to complete the conversion. Table says 0 produced this month, cumulative production total 61.

April 1952

Shortage of some supplies required by the GAF for the conversion for GR of the twelve Lincoln aircraft remaining to complete this project and of eight more aircraft to be returned from service by the RAAF affected progress during April. The prototype of the conversion project was completed to the flight trail stage minus some of the parts stipulated for complete modification and it is anticipated that the initial flight tests of this aircraft will commence in June. The cumulative effect of the shortages has necessitated the preparation of a new delivery schedule providing for the twenty aircraft to be delivered from July 1952 to March 1953. Table says 0 produced this month, cumulative production total 61.

May 1952

During May, ten test flights were carried out with Lincoln aircraft number 48 which had been converted by the GAF for GR purposes as the prototype of the conversion project, involving extensive modifications to the last twelve of the Lincolns to be delivered to the RAAF in the completion of the production of 73 of these aircraft plus eight aircraft to be returned from service. The trials were arranged to test the stability of the aircraft during flight and the effectiveness of the window deflectors and other fittings. Concurrently with the prototype tests, as much work as possible, having regard to the non availability of certain parts from overseas, was done on one aircraft returned by the RAAF and the remainder of the production aircraft. Table says 0 produced this month, cumulative production total 61

June 1952

Initial flight trials with Lincoln aircraft No, 48, which is being modified by the GAF as the prototype of the GR conversion project involving extensive modifications to 20 Lincoln aircraft for the RAAF, indicated the necessity for minor changes to be effected to the deflectors and some of the fittings of the aircraft. These were in progress at June 30.  Concurrently, production aircraft still to be delivered to complete the Lincoln project were being modified as far as possible having regard to the delays being experiences in the receipt of supplies from overseas. Table says 0 produced this month, cumulative production total 61.

July 1952

 Apart from certain new requirements of the RAAF in regard to the conversion of 20 Lincoln aircraft for GR purposes that were in the course of being engineered at July 31, the main outstanding matter affecting the delivery of the first few aircraft at that date was the non availability of parts on order from overseas. Within the limits of these shortages, as much work as possible was in progress on the conversion of the aircraft remaining to complete the production project and on two aircraft that had been returned by the RAAF for repair and overhaul. Table says 0 produced this month, cumulative production total 61.

August 1952

Certain of the items required by the GAF for the conversion of 20 Lincoln aircraft for GR purposes were still undelivered from overseas and local sources at August 31.  In the light of this position, the RAAF decided to accept delivery of the prototype aircraft "short fitted" and delivery on this basis will be affected, it is anticipated, during September.  Subsequent converted aircraft may be accepted by the RAAF on a similar basis. These developments will necessitate revision of the delivery schedule for this project. No table included in report.

Also included in the file is GAF Report number 80, August 1953, dated 5th September 1952, headed Lincoln Bomber Project. 

(a) Production.  The number of aircraft delivered to the RAAF remains at 61. The remaining 12 are to be converted to GR before delivery. 

(b) Major modifications, cumulative to 31 July are, 826 submitted to L.M.C, 749 effective aircraft determined, 32 balance under review.

Cumulative to 2nd September, 828 submitted to L.M.C, 802 effective aircraft determined, 26 balance under review.

(c) Conversion of 20 Lincolns for G.R. The total of 20 is made up of 12 new aircraft still to be delivered plus 8 returned from the RAAF. There is still a considerable number of shortages from overseas and local sources that are required to incorporate all the modifications at present desired by the RAAF, and until these shortages are covered, actual delivery dates are difficult to forecast.

The matter was discussed with the Resident Technical Officer last month with a view to our delivering aircraft short fitted of certain items, but we are now in receipt of memorandum from him stating that aircraft 48 can be delivered short fitted of certain items as a prototype but that the remaining aircraft should have all the local parts incorporated before delivery although the RAAF may agree to short fitment of some overseas parts. In view of this, the whole position is being reviewed with a view to revising the schedule of delivery. The position of the most advanced aircraft is,

A/C 48: Modified by our Experimental Engineering Workshop as a prototype; will be delivered early in September short fitted of certain items.

A/C 28: Returned from the RAAF and held in our Servicing Dept. awaiting incorporation of required parts as they come to hand.

A/C 62, 63: These are new aircraft and are practically due for delivery as soon as missing parts are received..

A/C 57: Returned from the RAAF and being worked on in Servicing.

(d) Repair and modification.  The following aircraft are now in the Plant:

A/C 28, 57, GR aircraft,

A/C 38: Scheduled for 29 Oct 1952,

A/C 3: Scheduled for 28 Nov 1952. 

(e) Spares.  Items urgently required by the RAAF are being supplied to the satisfaction of the RAAF E.L.O.

September 1952

Production report.  The prototype Lincoln aircraft converted for operation in the GR role was delivered to the RAAF during September, short fitted in respect of certain items of equipment. The RAAF has advised that the remaining 19 GR Lincolns will be accepted without certain items of equipment that have not yet been supplied from overseas but that all equipment of local origin is to be installed before the aircraft will be taken over.  The delivery program is, consequently, being re-planned. Table says 1 produced this month, cumulative production total 62.

October 1952

Shortage of certain essential items on order from overseas and local sources prevented the GAF completing during October the conversion of further Lincoln aircraft for GR purposes. There were 19 aircraft still to be converted at October 31 and although the RAAF has decided that these will be accepted minus certain of the imported items, the absence of these supplies has, in some instances, prevented the fitment of such local items that are available. However, it is anticipated that four aircraft additional to the one delivered in September will be delivered before December 25, 1952. A new schedule is being planned on this basis. Table says 0 produced this month, cumulative production total 61, the cumulative total is noted as amended. It is down by 1 from September.

November 1952

No deliveries of Lincoln aircraft converted for GR purposes were made by the GAF during November. At the end of the month, there were still 19 of the 20 aircraft, comprising 12 of the original order of 73 aircraft and seven to be returned from service by the RAAF, remaining to complete this project. Progress on these has been retarded because of the shortage of certain essential items from overseas and local services. However, agreement was reached with the RAAF during the month as to the modifications that are to be incorporated before delivery and concessions were raised covering the short fitment of the few overseas items that are not yet available. In the light of these concessions, it was anticipated that a number of the converted aircraft would be delivered during December. Table says 0 produced this month, cumulative production total 61.

December 1952

Two Lincoln aircraft converted for GR purposes were delivered by the GAF during December leaving ten production aircraft and six aircraft to be returned by the RAAF still to be completed to finalize the conversion project. Total deliveries of new Lincoln aircraft against the current order for 73 was 63 at December 31, 1952.  Table says 2 produced this month, cumulative production total 63.

January 1953

Although no new Lincoln aircraft converted for GR purposes were delivered to the RAAF by the GAF during January and total deliveries of these aircraft remained at 63 at the end of the month, an aircraft that had been returned by the RAAF especially for the conversion work was completed and redelivered to the Service during the period.  At January 31, the aircraft remaining to complete the conversion project comprised ten new and five RAAF aircraft, a total of 15. Table says 0 produced this month, cumulative production total 63.

February 1953

One new Lincoln bomber aircraft converted to GR purposes was delivered to the RAAF by the GAF during February leaving nine aircraft to complete the project of 73 aircraft of which the last twelve together with eight to be returned by the RAAF were to be converted to the GR role.  Of the total of 20 aircraft to be so modified six had been completed and delivered to the RAAF at the end of the month. Table says 1 produced this month, cumulative production total 64.

March 1953

During March, one new Lincoln bomber aircraft converted to the GR role was delivered to the RAAF by the GAF. At the end of the month eight new production aircraft plus five to be returned by the RAAF, a total of 13 aircraft remained to complete to the GR project.  They are scheduled for completion by July 1953.  Table says 1 produced this month, cumulative production total 65.

April 1953

One new Lincoln bomber aircraft converted for GR operations was completed by the GAF during April but delivery to the RAAF was not effected pending completion of experimental work in connection with Project "J". An aircraft returned by the RAAF for conversion to the GR role was completed and redelivered to the Service during the month.  Table says 0 produced this month, cumulative production total 65.

May 1953

The 66th Lincoln bomber aircraft, after conversion for GR operations, was delivered to the RAAF by the GAF during May.  Seven more Lincolns to a total of 73 aircraft remain to complete the project at May 31.  These will be converted to the GR role before delivery together with seven other Lincolns which are to be returned to the Factories by the RAAF for the conversion work,  Table says 1 produced this month, cumulative production total 66.

June 1953

One Lincoln bomber aircraft was delivered to the RAAF by the GAF during June.  Total deliveries at June 30 were 68 aircraft.  Concurrently with production, the last twelve of the project total of 73 aircraft are being extensively modified for GR purposes together with seven Lincoln aircraft to be returned by the RAAF for modification during normal repair and overhaul.  At June 30 eleven aircraft had been modified to the GR role of which ten had been delivered to the RAAF and one held at the factory for experimental purposes in connection with Project "J".  Table says 1 produced this month, cumulative production total 67.

July 1953

Three Lincoln bomber aircraft were delivered to the RAAF by the GAF during July after extensive modifications had been made to the aircraft during production to convert them for the anti submarine role.  Total deliveries at July 31 were 70 aircraft.  The three aircraft remaining to complete the Lincoln project will also be converted to the same purpose as portion of the RAAF requirements for the conversion of Lincoln aircraft for GR work, comprising twelve new aircraft and seven returned from service by the RAAF.  Five of these aircraft remain to complete the conversion project.  Table says 3 produced this month, cumulative production total 70.

August 1953

During August, one Lincoln aircraft, was delivered to the RAAF by the GAF after conversion to the GR role had been affected concurrently with production. Two aircraft remained at August 31 to complete this project - both are also to be converted to anti submarine operations.  Table says 2 produced this month, cumulative production total 71. (so it looks like 1 was produced)

No September 1953 report in file. 

No mention of Lincolns in October 1953 onwards reports, so it is assumed the final 2 new Lincolns were built in September 1953.

The above information was provided by Mr. Geoffrey Sinclair.

Updated 1st May 2015

 
 

 

 

It is our policy to only show historical events, no current operational information will be displayed on this website.
 "The ADF/Serials team give permission to use the content of this page, excluding images, providing that it contains an acknowledgement to the adf/serials team and any other listed sources."